Construction Projects

Summer & fall is the time when visible – and possibly impactful – construction projects begin and end. When town construction projects are in progress, we will list those here. Activity is subject to change without notice.

VILLAGE POND MAINTENANCE DREDGING PROJECT | 100% COMPLETE

In conjunction with Western Stream Works, LLC., The Town of Mountain Village (TMV) drained, dredged and renovated the Village Pond located adjacent to the Telluride Conference Center.

The work performed is to maintain the health of the pond by mitigating the accumulation of sediment over the years of sediment transfer during precipitation and spring runoff events.

ROAD ASPHALT PAVING | 100% COMPLETE

The Town of Mountain Village performed asphalt paving road work, Friday, July 26, 2019 beginning at 7 a.m. through Aug. 10. The project will improve and prolong the life of the road surface.

The Market Plaza parking lot will be closed for repaving of the asphalt surface on Monday, August 5. Market Plaza businesses will remain open, but please use the Gondola Parking Garage for parking during this time.

ROAD CHIP SEAL MAINTENANCE | 100% COMPLETE

The Town of Mountain Village will perform chip seal operations in Mountain Village, Monday, July 30 through August 2 beginning at 8 a.m. The project will improve and prolong the life of the road surface.

United Companies has been contracted to chip seal the following roads:

  • Aspen Ridge Drive
  • Vischer Drive
  • Victoria Drive
  • Stevens Drive
  • Hanglider Drive
  • Gold Hill Court
  • Benchmark Drive from Rocky Road to the Cul-de-sac
  • San Sofia Drive

TELLURIDE SKI & GOLF CELL TOWER PROJECT | 55% COMPLETE

The proposed new lattice communication tower would be located on Telluride Ski & Golf Company’s (TSG) open space on the Ridge near the top of Station St. Sophia, and next to the existing 90-foot KOTO tower. Construction of an access road to begin cell tower installation is pending until further notice to install the 100-foot tower on Coonskin Ridge.